Caught in the Doldrums: A Clean-Seas Update

Share

Clean-Seas West Virginia now has an air quality permit in hand but does this mean that the facility will soon begin operations? Read on to learn more about what’s happened since we published our recent report and what to look for in the months ahead.

On August 12, 2026, the West Virginia Department of Environmental Protection issued an air quality permit for Clean-Seas West Virginia, Clean Vision Corporation’s flagship plastics pyrolysis facility in the U.S. This permit designates the project as a manufacturing facility, allowing it to evade more stringent regulations designed to protect host communities from the most damaging impacts of waste incineration. This decision came nearly a year after the company first submitted its permit application and over three years since the facility was first announced.

In a press release issued two days after receiving the permit, CEO Dan Bates was quoted as saying that the company has “reached the point where Clean-Seas West Virginia can move forward… toward commercial-scale operations.” Missing from this 700-word release were a number of key details regarding facility development, such as: an updated timeline for initiating operations; whether the company has complied with the terms of its two state-facilitated loan agreements, including benchmarks related to employment and equipment delivery; and, most importantly, the status of the financing for the facility.

Project Financing

While regulatory approval is a critical milestone for any industrial project, the ability of Clean-Seas to actually produce its promised pyrolysis oil ultimately depends on it securing the necessary capital to finance commercial operations. A 2023 press statement indicated that the facility would require a $65 million investment, an amount that likely reflects plans to scale up well beyond the company’s current permitted capacity of 51 tons per day (tpd). The company has so far not disclosed whether it has secured the financing required to move ahead now that it has received its permit. However, as of March of this year, the company still needed “seventy-five to a hundred grand in cash” before the company’s one-ton training unit could be brought online and “probably six to eight million” for the 25-ton pyrolysis unit to be brought online (see timestamp 42:38).

As discussed in A Deep Dive into Clean-Seas, our report detailing Clean Vision Corporation’s financial and operational history, the facility’s advantageous manufacturing designation depends, in part, on its ability to succeed as a commercial enterprise:

If Clean-Seas West Virginia is successful in securing this manufacturing designation, it will also have to “demonstrate that the pyrolysis oil is continuously managed as a valuable commercial product and not speculatively accumulated or discarded,” which will be largely dependent on its ability to secure commercial agreements with off-takers, refineries, or secondary markets.

A 2024 video from Clean Vision Corporation claimed that “global offtake contracts are in final negotiations and will be announced soon.” Bates echoed this claim in a letter to shareholders earlier this year, stating that Clean Vision Corporation expects to complete “final negotiations for an off-take agreement with a… multinational petrochemical company”. However, at the time of writing, the company has yet to announce a buyer for its pyrolysis oil and it’s unclear whether the company has secured all the equipment required to operate at its permitted 51-tpd capacity.

New Warning Signs

Since we published our report, Clean Vision Corporation’s financial standing has only become more problematic. On September 23rd, the company filed its first and second quarterly report of the year, well after it had typically filed them in previous years. The second of these indicates that the company’s accumulated deficit — its operating losses combined with other expenses — has grown to over $61 million.

Notably, the company also reported no revenue for the first six months of the year — the first time this has happened since 2023. As discussed in our full report, the company has failed to reach its annualized revenue goal of “around $1.25 million” for its lone commercial facility and has so far recorded year-over-year declines in revenue. However, this development — the lack of reported revenue — is significant.

Adding to the company’s issues is the fact that it was “unable to obtain financial information from [its] subsidiary in Morocco” for these two quarters, an admission that hints at potential management issues or possibly to challenges preparing accurate and timely financial statements, also evidenced by the fact that the company recently published, for the first time since its shift to plastics pyrolysis, an annual report with unaudited financial statements.

Meanwhile, payments from the company’s $15 million commercial loan appear to have mostly stopped. Disbursements in 2025 totaled $7.4 million but the latest balance sheets record only $10,411 for the first six months of 2026. This loan, arranged by the state and currently held by Huntington Bank, was to be awarded in tranches of $5 million and $10 million instead of the variable amounts reflected on the company’s 2025 balance sheets. The conditions under which these payments were disbursed and, more importantly, why they largely stopped, as shown by the two latest filings, remain unclear.

These new filings also indicate that the Belle facility “is currently expected to be operational in Q1 2027” — its seventh delay since it was first announced in 2023 — and that the company plans to “expand to greater than 100 tpd within three years of beginning operations.” As discussed in our report, Clean Vision Corporation does not have a strong track record for developing facilities, let alone expanding them. In the five years since the company began focusing on plastics pyrolysis, it has only initiated operations at two sites, despite announcing plans for at least fourteen facilities in eight different countries. Of these two operational sites, just one has been reported as generating revenue — the same site for which Clean Vision Corporation was unable to report revenue in its last two quarterly reports.

The share dilution evident over the last several years offers further evidence of the company’s challenges. Clean Vision Corporation’s latest filing records 1,781,884,801 outstanding shares — a 39% increase in just six months. Most of these new shares were issued through debt conversions, an arrangement that allows borrowers or lenders to exchange debt for equity in a company.

Market Signals

Clean Vision Corporation’s share price has, for the most part, failed to reward the company for its efforts to develop plastics pyrolysis facilities, a trend that has continued even after the company received its permit. Since acquiring its Clean-Seas subsidiary in 2020, the CLNV share price has never closed higher than thirty-six cents. The price dropped even further as the company set its sights on developing a pyrolysis facility in West Virginia. Since then, the company’s share performance shows a series of brief increases, each typically smaller than the last and each followed by a subsequent drop.  

CLNV Share Price, 03/01/2023 – 10/01/2026

That the share price has, on the whole, performed worse the closer the company moves towards operations in Belle is a counterintuitive but telling market signal. Even more sobering is the fact that, in the context of its prior performance, the share price over the last several years has more or less been flat.

What’s Past is Prologue

In 2021, the Indiana Business Journal published an article about the “rise and fall” of Indiana-based WindStream Technologies, founded in 2008 by Dan Bates, now CEO of Clean Vision Corporation:

Behind the scenes, WindStream was scrambling for money, as expenses were soaring and loans were coming due. The company’s stock had dropped to pennies on the over-the-counter exchange. Executives were selling off company equity and taking on debt to try to keep the enterprise afloat.

Clean Vision Corporation later sought to acquire WindStream Technologies’ assets after WindStream was delisted from NASDAQ in 2019. In 2022, a federal judge ordered WindStream and Bates to pay $4.5 million after the company defaulted on a private loan guaranteed by Bates but, as of December 31, 2024, no payment had been made.

Like WindStream, Clean Vision Corporation has failed to generate a meaningful amount of revenue and has taken on debt to support operations, including loan agreements facilitated by the State of West Virginia adding up to $16.75 million. While we don’t know what the future holds for this company nor can we fully account for the impact of the facility’s new air quality permit — Clean Vision Corporation’s next filing, expected later this year, will be our first full window into the company’s status post-permitting — the company’s history to date provides sufficient cause for skepticism.

Learn more about Clean Vision Corporation’s financial and operational track record by reading our report, A Deep Dive into Clean-Seas: Rough Waters for Belle Plastics Pyrolysis Facility. For further information about plastics pyrolysis and similar projects in Appalachia, read our 2024 report, Chemical Recycling: A False Promise for the Ohio River Valley

RELATED ARTICLES

Sign up for our newsletter

Receive our latest research and messaging strategies

News Letter Subscription Vertical

RELATED ARTICLES

Sign up for our newsletter

Receive our latest research and messaging strategies

Newsletter Subscription Vertical Mobile

All of our research is available to you to cite, use, and share, per our free use policy. Let’s Face Our Challenges Together!

|

Nov 13, 2026
Data centers impose major costs and “crowding out” effects that are unavoidable—and rarely acknowledged by economic impact studies.

Written by

|

Oct 30, 2026
Gas-powered data centers and LNG exports are fueling a new wave of investment in pipelines to ship fracked gas out of Appalachia.

Written by